What is the logic behind the recalculate option in the timesheet page.?

Jan 17, 2011 at 10:13 PM

Hi All,

I am using Project server 2007 with sp2 and SQL server 2005 with latest SP.

I am trying to add a javascript to my timesheet page which actually does some calculations and modifies the cell values in the grid.This happens when a custom button on the page is clicked.

The javascript gets executed properly and the modified values are seen in the grid.

The issue comes when I click on recalculate or save button, which actually erases my modified values and retains the old values as the postback happens on click of recalculate/save buttons.

Can anyone tell me where the data is temporarly stored while the page is postback.

Please suggest how I will be able to submit the modified values (updated with script).

Pls suggest.

 

Regards,